Our Restoration Project has begun!


We're excited to share that our Capital Campaign has been incredibly successful, and thanks to the generosity of our donors, Phase 1A funding has been achieved, and construction to restore our beautiful building is now underway.


Contributions have come in all sizes, from individual donations, grants, and fundraising events, with amounts ranging from $25.00 to over $200,000. We truly appreciate the support from everyone involved as we move forward with this important project.


Construction to restore our historic building is underway. The Phase 1A structural work and demolition has been completed.  Work is now scheduled to complete all tasks listed under Phase 1A.
 

Join us in our exciting journey as we renovate our historic building!

We thank you for your continued support!

Asbestos Abatement

The last remnants of the building's original heating system have now been removed from TCFA.

Selective Demolition


Sinks, toilets, and tile have been removed from our bathrooms and reception area revealing beautiful softwood pine! Removal of the famous fiber board in the Lobby uncovered our remaining plaster and is giving more insight on the scope of the project.

Tree Removal

Our second sugar maple was removed from the front lawn of TCFA, and not a moment too soon.

Dead branches were also removed from trees in our backyard.

We will be planting new trees in the front after the renovation construction is complete.


We Lifted the Building

Structural work began by lifting the south wall of the building.  Subsequent work will provide additional support and help level the floor.


Inside, the conduit has been removed, and protective material has been laid on our dance floor to prepare for demolition.


Look at our Bones!


We are beginning to see what is behind the fiberboard and plaster. The lobby has been cleared, and it provides a good look inside of our beautiful building.


Our Masonry Work has been completed

The structural foundation is being repaired, both inside and outside, which includes the base of the columns.


This work also addresses previous patchwork repairs in order to ensure we stand strong for another 150 years.



Our beautiful entry...

We’re thrilled to announce the restoration of TCFA's beautiful entry is underway!


Our general contractor, Bouley Associates, has begun work by installing protective fencing around the front of

the building.

Our front porch

The old ramp has been removed, exposing the portico deck framing. While the timbers are in remarkable condition given their age, some sections along the front edge have deteriorated. The deck floor joists rest on loose stone piles, which will need to be reconstructed. We have also inspected the backs of the stone column bases and found them to be in very good shape.



The old deck sloped four inches from the exit doors to the edge, which exceeds the maximum allowable slope under current building codes. The current plan is to raise the outer edge of the deck to achieve proper compliance while preserving the historic appearance of the front facade.

The architect is working on a solution to address this issue.

Building from the Ground Up

1. Lifting the building

2. Securing the foundation

3. Repairing the masonry

4. Replacing rotted wood

5. Sanding and painting

Our Historic Exterior is Coming to Life!

Moving from the old to the new.

The work has also included window and gutter repair.

Returning to the Original Look

Our historic photos paved the way for color selection as we continue our restoration of the historic exterior.


Progress on the Front Porch and ADA Compliant Ramp

Progress on the restoration of our Historic Exterior is coming along nicely. Our exterior doors have been removed for restoration off-site.



With the announcement of a second NYSCA grant, plans are in place to begin our Historic Interior restoration soon.

Read More